The planned annual repairs of Unit VI of Kozloduy NPP have been completed five days ahead of schedule. On November 1, at 1.41 am, it joined the country's energy system after an inspection and approval by the Nuclear Regulatory Agency.
The unit was stopped on September 29. For 31 days, the capacity of 1,000 megawatts was not part of the electricity market, which caused further rise of energy prices in Bulgaria.
Equipment maintenance has been performed and the unit has been refueled with fresh nuclear fuel. All the planned activities related to increasing the safety and ensuring the long-term operation of the unit have been carried out. The 5th nuclear power unit of Kozloduy is also operating at full capacity, the power plant's head Nasko Mihov said.
The Bulgarian Ministry of Defense has signed a contract with Polish state company Wojskowe Zakłady Lotnicze Nr 2 S.A. for major repair of six MiG-29 aircraft engines. The maximum period for carrying out the repair of each engine will be no more..
The chief of police in Petrich and two other police officers, arrested two days ago, are accused of participating in a criminal group. This was announced by Sofia city prosecutor Iliana Kirilova, BTA reported. According to Kirilova, the detained..
The Sofia City Prosecutor's Office has announced the release of Dzheyhan Ibryamov. He will be released from custody tomorrow, November 7, and the investigation against him on charges of influence peddling will be suspended at the moment he takes the..
2.5% is the necessary effort that our country must make in terms of defence spending, caretaker Minister of Defense Atanas Zapryanov..
Acting Energy Minister Vladimir Malinov told a briefing that neither he nor the Energy Ministry had any information about the sale of Lukoil Neftohim..
The Bulgarian Ministry of Defense has signed a contract with Polish state company Wojskowe Zakłady Lotnicze Nr 2 S.A. for major repair of six MiG-29..
+359 2 9336 661