Full capacity of gas interconnector with Greece has been reserved

Photo: icgb.eu

“92% of the Gas Interconnector Greece-Bulgaria, ICGB, is ready. The interconnector will be ready by the end of June, and will be tested with gas as of July,” Teodora Georgieva, Bulgarian Executive Officer of the company ICGB which is constructing the interconnector said for public service TV BNT.

"The 182-km. long linear part of the pipeline is ready. The pipes have been laid and covered, tests have been conducted. Besides Covid-19, the construction work has also been slowed down by delayed crane deliveries, but they too have now been tested. What remains is the construction of the gas stations in Stara Zagora in Bulgaria and in Komotini in Greece. The construction company is due to pay damages of EUR 90,000 per every day of delay after the beginning of 2022. The pipe’s capacity, which is 3 million cubic metres, and it has already been reserved," Teodora Georgieva said. 



Последвайте ни и в Google News Showcase, за да научите най-важното от деня!
Listen to the daily news from Bulgaria presented in "Bulgaria Today" podcast, available in Spotify.

More from category

International Technical Fair 2025 kicks off in Plovdiv

Plovdiv is hosting the 79th International Technical Fair from September 24 to 27, 2025 , bringing together leading companies, innovators, and industry professionals. The Forum highlights technological advancement and sustainable development across key..

published on 9/24/25 8:55 AM
Fabian Bornhorst, head of the IMF mission in Bulgaria (R), and Svetlomira Porova, journalist at Capital Daily.

IMF: Bulgaria must strengthen fiscal discipline

Bulgaria has the opportunity to reap the full benefits of eurozone membership , but this will require stronger fiscal discipline, effective management of transition risks, and accelerated structural reforms , the International Monetary Fund (IMF)..

published on 9/23/25 5:16 PM

Bulgaria's wine sector sees poor grape harvest amidst growing investment interest

In mid-September, the traditionally great Christian feast of the Holy Cross (September 14) marks the beginning of one of the most anticipated agricultural processes – the grape harvest campaign. 2025 is no exception, but due to a number of factors, the..

published on 9/18/25 1:10 PM